May Building

May has been a busy month for building The Cabin Heat Control was completed and the Radiator Installed The Fuel Tank in now in place and the Seat Belts attached The Canopy is getting...

0

Week 11 and 12

Work has continued on the RV12. The team has learned more about working with Fibreglass as they create the fairing for the front of the Canopy. The Engine Cowl is getting closer with another...

0

2016 – Week 9

Julia and Even started off the night by installing the Canopy Latch David and Rylan were busy countersinking the hinge that attaches the upper and lower Engine Cowl Callum riveted the ADAHRS stiffening bracket...

0

2016 – Week 3

Week 3     The Rear Window was drilled and screwed. Sealant was used to keep water from leaking inside.   Cowl Hinges were installed       The Lower Cowl was aligned and...

0

2016 – Week 1

Teenflight Campbell River is back for the first time in 2016 after the Holiday Break After being away for a few weeks, everyone read over the plans to make sure they had a plan...

0

Helifor Tour

The TeenFlight Campbell River Crew got a tour of a Helifor Helicopter this past weekend   The S-64 Erickson Air-Crane was originally designed by Sikorsk as the S-64 Skycrane   General characteristics Crew: 3...